Background
The wood treatment facility had been in operation for some 90 years
and ceased its operations in 1989. Creosote contamination
was a result of daily operations, accidental spills, bombings during
World War II and, more recently, a fire. The average concentration
level of PAHs was 5,200 ppm, including heavily contaminated
lots bearing concentration levels up to 28,000 ppm. The targeted
criterion for TPAHs was established at 400 ppm.
Solution
On the basis of the treatability study results, Biogenie proposed
a biological treatment solution which bore guarantees in terms
of performance, cost and treatment time. Biogenie’s ex situ Biopile treatment process was applied to 6,200 tons
of PAH-contaminated soil. Biogenie was able
to reach the treatment objectives within the guaranteed time frame.
Services
- Treatability
study to confirm the viability of a biological treatment solution
and to determine optimal biotreatment paramaters;
-
Ex situ
Biopile treatment of 6,200 tons of soil in order to
meet standards established for industrial use;
- Treatment
of groundwater containing heavy creosote concentrations using
a "pump & treat" method.